The wax mold making process is a very important step in the process of investment casting, which is mainly used to make wax molds in investment casting, the specific role is as follows:
Manufacture of precision wax molds: The wax mold making process is carried out by injecting melted medium temperature wax into the molds, which is then cooled and solidified, resulting in precise wax molds that will be used as molds for subsequent casting;
Accurate Reproduction: The wax molding process reproduces the details and shapes of the prototype to ensure the precision and accuracy of the final graduation;
Preparation for investment casting: The wax mold making process provides the preparation for the subsequent investment casting and ensures high quality castings during the casting process;
In conclusion, the quality of control of the wax mold making process directly affects the quality of the wax mold and indirectly affects the quality of the final casting blanks, so it is a crucial link in the whole investment casting process.
The working hours of our wax shop,AM:7:45~11:15,PM:12:15~16:45,
Job Description:
- Our workshop team leader will arrive at the scene 30 minutes in advance to carry out the daily inspection of equipment in the workshop, the inspection content includes: 1) hydraulic operating mechanism lubrication, not lower than the equipment oil level meter scale; 2) whether the state of the switch is normal, intact, not loose, elasticity is normal, consistent action; 3) whether the cooling water valve is normal to open; 4) whether the hydraulic pump is running normally, no abnormal noise, abnormal heat, each Pressure gauge display is normal (required pressure range of 250-800Psi), pressure, flow rate adjustment knob is normal, whether the position is changed; 5) whether the temperature control meter display is normal (storage wax cylinder temperature 78-84 ℃, cooling cylinder temperature 55-60 ℃, wax cylinder temperature 55-60 ℃); 6) the time control meter shows the value of the normal, no inaccurate value and does not show bad; 7) The equipment is clean, the machine is clean, no residual wax, dust, oil, etc.; after the inspection, output the results of the inspection, and confirmed by the director of the casting plant, if there is any abnormality, notify the maintenance personnel to carry out maintenance in time;
- Fifteen minutes before the start of work, employees arrive at the work site, in the designated location, the team leader presided over the morning meeting work, the implementation of the day's production plan, precautions and the quality of the previous problems;
- Start the equipment, make the first piece of wax mold, the team leader inspect the first piece of wax mold, and record the inspection data and archive;
- If there is no abnormality in the first piece inspection, the staff will carry out normal production according to the production plan of the day;
- Five minutes before the end of the shift, clean the workbench space, turn off the production equipment, and the team leader turns off the power to the shop;
This is a day of our wax workshop daily work, our company has more than 20 years of experience in the investment casting industry, and with a number of well-known enterprises to support, know that only control every detail of the manufacturing process, in order to ensure the quality of the final product, so, all along, the company's senior management attaches great importance to the control of the wax workshop.